GET /project/{projectId}/scenario/{scenarioId}/critical-path-changes

Headers

  • X-COMPANY-ID string Required

    The company's unique ID

Path parameters

  • projectId integer(int64) Required
  • scenarioId integer(int64) Required

Query parameters

  • dataDate string

Responses

  • 200 */*

    OK

    Hide response attributes Show response attributes object
    • added array[object]
      Hide added attributes Show added attributes object
      • performanceTrack boolean
      • percentCompleteType string

        Values are DURATION, PHYSICAL, or UNITS.

      • updatedPlannedDurationHours number(double)
      • notComplete boolean
      • calendarId integer(int64)
      • customId string
      • constrainedDate string(date-time)
      • resumeDate string(date-time)
      • updatedPlannedDuration number(double)
      • externalProjectId integer(int32)
      • plannedDuration number(double)
      • plannedDurationHours number(double)
      • plannedManpower number(double)
      • actualManpower number(double)
      • plannedBudget number(double)
      • plannedStartDate string(date-time)
      • plannedFinishDate string(date-time)
      • percentComplete number(double)
      • nativeFloatTotal number(double)
      • remainingDurationHours number(double)
      • actualDuration number(double)
      • actualDurationHours number(double)
      • actualStartDate string(date-time)
      • actualFinishDate string(date-time)
      • activityType string

        Values are TaskDependent, Task, StartMilestone, FinishMilestone, or LevelOfEffort.

      • constraintGenerated boolean
      • wbsCodeId integer(int32)
      • retainLogic boolean
      • externalId string
      • isExcludeFromProgress boolean
      • physicalPercentComplete number(double)
      • unitsPercentComplete number(double)
      • conditionalBreakType string

        Values are TimePeriod, Shift, or WorkPattern.

      • startOnNewDay boolean
      • sourceStartDate string(date-time)
      • sourceFinishDate string(date-time)
      • sourceActualStartDate string(date-time)
      • sourceActualFinishDate string(date-time)
      • sourceDurationPercentComplete number(double)
      • name string
      • id integer(int64)
      • started boolean
      • completed boolean
      • constraintType string

        Values are AsLateAsPossible, FinishOn, FinishOnOrAfter, FinishOnOrBefore, MandatoryFinish, MandatoryStart, StartOn, StartOnOrAfter, StartOnOrBefore, ExternalStart, or Resume.

      • order integer(int32)
      • startDate string(date-time)
      • finishDate string(date-time)
      • deleted boolean
      • floatTotal number(double)
      • floatFree number(double)
      • lateStartDate string(date-time)
      • lateFinishDate string(date-time)
      • remainingDuration number(double)
      • predecessorDrivers array[integer(int64)]
      • inLongestPath boolean
      • scenarioId integer(int64)
      • dateCreated string(date)
    • removed array[object]
      Hide removed attributes Show removed attributes object
      • performanceTrack boolean
      • percentCompleteType string

        Values are DURATION, PHYSICAL, or UNITS.

      • updatedPlannedDurationHours number(double)
      • notComplete boolean
      • calendarId integer(int64)
      • customId string
      • constrainedDate string(date-time)
      • resumeDate string(date-time)
      • updatedPlannedDuration number(double)
      • externalProjectId integer(int32)
      • plannedDuration number(double)
      • plannedDurationHours number(double)
      • plannedManpower number(double)
      • actualManpower number(double)
      • plannedBudget number(double)
      • plannedStartDate string(date-time)
      • plannedFinishDate string(date-time)
      • percentComplete number(double)
      • nativeFloatTotal number(double)
      • remainingDurationHours number(double)
      • actualDuration number(double)
      • actualDurationHours number(double)
      • actualStartDate string(date-time)
      • actualFinishDate string(date-time)
      • activityType string

        Values are TaskDependent, Task, StartMilestone, FinishMilestone, or LevelOfEffort.

      • constraintGenerated boolean
      • wbsCodeId integer(int32)
      • retainLogic boolean
      • externalId string
      • isExcludeFromProgress boolean
      • physicalPercentComplete number(double)
      • unitsPercentComplete number(double)
      • conditionalBreakType string

        Values are TimePeriod, Shift, or WorkPattern.

      • startOnNewDay boolean
      • sourceStartDate string(date-time)
      • sourceFinishDate string(date-time)
      • sourceActualStartDate string(date-time)
      • sourceActualFinishDate string(date-time)
      • sourceDurationPercentComplete number(double)
      • name string
      • id integer(int64)
      • started boolean
      • completed boolean
      • constraintType string

        Values are AsLateAsPossible, FinishOn, FinishOnOrAfter, FinishOnOrBefore, MandatoryFinish, MandatoryStart, StartOn, StartOnOrAfter, StartOnOrBefore, ExternalStart, or Resume.

      • order integer(int32)
      • startDate string(date-time)
      • finishDate string(date-time)
      • deleted boolean
      • floatTotal number(double)
      • floatFree number(double)
      • lateStartDate string(date-time)
      • lateFinishDate string(date-time)
      • remainingDuration number(double)
      • predecessorDrivers array[integer(int64)]
      • inLongestPath boolean
      • scenarioId integer(int64)
      • dateCreated string(date)
GET /project/{projectId}/scenario/{scenarioId}/critical-path-changes
curl \
 --request GET 'https://live.smartpmtech.com/project/{projectId}/scenario/{scenarioId}/critical-path-changes' \
 --header "X-API-KEY: $API_KEY" \
 --header "X-COMPANY-ID: string"
Response examples (200)
{
  "added": [
    {
      "performanceTrack": true,
      "percentCompleteType": "DURATION",
      "updatedPlannedDurationHours": 42.0,
      "notComplete": true,
      "calendarId": 42,
      "customId": "string",
      "constrainedDate": "2026-05-04T09:42:00Z",
      "resumeDate": "2026-05-04T09:42:00Z",
      "updatedPlannedDuration": 42.0,
      "externalProjectId": 42,
      "plannedDuration": 42.0,
      "plannedDurationHours": 42.0,
      "plannedManpower": 42.0,
      "actualManpower": 42.0,
      "plannedBudget": 42.0,
      "plannedStartDate": "2026-05-04T09:42:00Z",
      "plannedFinishDate": "2026-05-04T09:42:00Z",
      "percentComplete": 42.0,
      "nativeFloatTotal": 42.0,
      "remainingDurationHours": 42.0,
      "actualDuration": 42.0,
      "actualDurationHours": 42.0,
      "actualStartDate": "2026-05-04T09:42:00Z",
      "actualFinishDate": "2026-05-04T09:42:00Z",
      "activityType": "TaskDependent",
      "constraintGenerated": true,
      "wbsCodeId": 42,
      "retainLogic": true,
      "externalId": "string",
      "isExcludeFromProgress": true,
      "physicalPercentComplete": 42.0,
      "unitsPercentComplete": 42.0,
      "conditionalBreakType": "TimePeriod",
      "startOnNewDay": true,
      "sourceStartDate": "2026-05-04T09:42:00Z",
      "sourceFinishDate": "2026-05-04T09:42:00Z",
      "sourceActualStartDate": "2026-05-04T09:42:00Z",
      "sourceActualFinishDate": "2026-05-04T09:42:00Z",
      "sourceDurationPercentComplete": 42.0,
      "name": "string",
      "id": 42,
      "started": true,
      "completed": true,
      "constraintType": "AsLateAsPossible",
      "order": 42,
      "startDate": "2026-05-04T09:42:00Z",
      "finishDate": "2026-05-04T09:42:00Z",
      "deleted": true,
      "floatTotal": 42.0,
      "floatFree": 42.0,
      "lateStartDate": "2026-05-04T09:42:00Z",
      "lateFinishDate": "2026-05-04T09:42:00Z",
      "remainingDuration": 42.0,
      "predecessorDrivers": [
        42
      ],
      "inLongestPath": true,
      "scenarioId": 42,
      "dateCreated": "2026-05-04"
    }
  ],
  "removed": [
    {
      "performanceTrack": true,
      "percentCompleteType": "DURATION",
      "updatedPlannedDurationHours": 42.0,
      "notComplete": true,
      "calendarId": 42,
      "customId": "string",
      "constrainedDate": "2026-05-04T09:42:00Z",
      "resumeDate": "2026-05-04T09:42:00Z",
      "updatedPlannedDuration": 42.0,
      "externalProjectId": 42,
      "plannedDuration": 42.0,
      "plannedDurationHours": 42.0,
      "plannedManpower": 42.0,
      "actualManpower": 42.0,
      "plannedBudget": 42.0,
      "plannedStartDate": "2026-05-04T09:42:00Z",
      "plannedFinishDate": "2026-05-04T09:42:00Z",
      "percentComplete": 42.0,
      "nativeFloatTotal": 42.0,
      "remainingDurationHours": 42.0,
      "actualDuration": 42.0,
      "actualDurationHours": 42.0,
      "actualStartDate": "2026-05-04T09:42:00Z",
      "actualFinishDate": "2026-05-04T09:42:00Z",
      "activityType": "TaskDependent",
      "constraintGenerated": true,
      "wbsCodeId": 42,
      "retainLogic": true,
      "externalId": "string",
      "isExcludeFromProgress": true,
      "physicalPercentComplete": 42.0,
      "unitsPercentComplete": 42.0,
      "conditionalBreakType": "TimePeriod",
      "startOnNewDay": true,
      "sourceStartDate": "2026-05-04T09:42:00Z",
      "sourceFinishDate": "2026-05-04T09:42:00Z",
      "sourceActualStartDate": "2026-05-04T09:42:00Z",
      "sourceActualFinishDate": "2026-05-04T09:42:00Z",
      "sourceDurationPercentComplete": 42.0,
      "name": "string",
      "id": 42,
      "started": true,
      "completed": true,
      "constraintType": "AsLateAsPossible",
      "order": 42,
      "startDate": "2026-05-04T09:42:00Z",
      "finishDate": "2026-05-04T09:42:00Z",
      "deleted": true,
      "floatTotal": 42.0,
      "floatFree": 42.0,
      "lateStartDate": "2026-05-04T09:42:00Z",
      "lateFinishDate": "2026-05-04T09:42:00Z",
      "remainingDuration": 42.0,
      "predecessorDrivers": [
        42
      ],
      "inLongestPath": true,
      "scenarioId": 42,
      "dateCreated": "2026-05-04"
    }
  ]
}