Get scenario metrics 2

Add MCP server to your AI tool

Allow AI tools and LLMs to interact with the API documentation portal through MCP.

MCP server URL

https://developers.smartpm.com/mcp

Standard setup for AI tools providing an mcp.json file

mcp.json
{
  "SmartPM Public API MCP server": {
    "url": "https://developers.smartpm.com/mcp"
  }
}

Close
GET /project/{projectId}/metrics

Headers

  • X-COMPANY-ID string Required

    The company's unique ID

Path parameters

  • projectId integer(int64) Required

Query parameters

  • dataDate string

Responses

  • 200 */*

    OK

    Hide response attributes Show response attributes object
    • projectId integer(int64)
    • modelId integer(int64)
    • name string
    • id integer(int64)
    • source string

      Values are SmartPM, XER, MPP, Excel, PMXML, PPX, or PP.

    • scenarioType string

      Values are COMPLETE or PARTIAL.

    • delayAnalysisPerformed string

      Values are No, InProgress, or Done.

    • dataDate string(date-time)
    • qualityIndex object
      Hide qualityIndex attributes Show qualityIndex attributes object
      • mark string
      • indicator string

        Values are GOOD, FINE, or BAD.

      • score number(double)
    • baselineStartDate string(date-time)
    • plannedRecovery integer(int64)
    • daysOfDelays integer(int64)
    • endDateVariance integer(int64)
    • underConstruction boolean
    • baselineEndDate string(date-time)
    • currentScheduledCompletion string(date-time)
    • previousScheduledCompletion string(date-time)
    • sourceEndDate string(date-time)
    • upgradePlans array[string]
    • percentCompleteType string
    • qualityProfileId integer(int64)
    • unreadNotes integer(int64)
    • plannedManpower number(double)
    • earnedManpower number(double)
    • remainingManpower number(double)
    • actualManpower number(double)
    • currentEstimatedManpower number(double)
    • plannedBudget number(double)
    • remainingBudget number(double)
    • earnedCost number(double)
    • manpowerPlannedPercentComplete number(double)
    • manpowerActualPercentComplete number(double)
    • manpowerPerformanceIndex number(double)
    • costPlannedPercentComplete number(double)
    • costActualPercentComplete number(double)
    • costPerformanceIndex number(double)
    • schedulePerformanceIndex number(double)
    • resourceCount number(double)
    • averageDurationVariance integer(int64)
    • baselineCompletionPlanned number(double)
    • baselineCompletionActual number(double)
    • completionPlanned number(double)
    • completionActual number(double)
    • performanceTrack boolean
    • costTrack boolean
    • scheduleCompressionIndex object
      Hide scheduleCompressionIndex attributes Show scheduleCompressionIndex attributes object
      • name string

        Values are ACTIVITIES_TOTAL, ACTIVITIES_MILESTONES, ACTIVITIES_ACTIVITIES, ACTIVITY_NAME_CHANGES, RELATIONSHIPS_TOTAL, RELATIONSHIPS_START_TO_FINISH, RELATIONSHIPS_START_TO_START, RELATIONSHIPS_FINISH_TO_START, RELATIONSHIPS_FINISH_TO_FINISH, MISSING_LOGIC, LAG_NEGATIVE, LAG_POSITIVE, CONSTRAINTS_TOTAL, CONSTRAINTS_HARD, CONSTRAINTS_SOFT, CONSTRAINT_BREAKING_LOGIC, LOW_FLOAT_ACTIVITIES, HIGH_FLOAT_ACTIVITIES, HIGH_DURATION_ACTIVITIES, RESOURCE_LOADED_ACTIVITIES, CRITICAL_PATH_PERCENT, AVG_ACTIVITY_TOTAL_FLOAT, SCHEDULE_COMPRESSION_INDEX, IMPORT_CHANGE_STARTED_NO_PROGRESS, IMPORT_CHANGE_FUTURE_ACTUAL_DATES, IMPORT_CHANGE_COMPLETE_BUT_NO_ACTUAL_FINISH_DATE, IMPORT_CHANGE_CHANGED_ACTUAL_DATES, IMPORT_CHANGE_DECREASED_PERCENT_COMPLETE, INVALID_FORECAST_DATE, MANUALLY_SCHEDULED_ACTIVITIES, DANGLING_ACTIVITIES, MANUALLY_SCHEDULED_SUMMARIES, DUPLICATE_RELATIONSHIPS, DUPLICATE_ACTIVITY_NAMES, IMPORT_CHANGE_LOGIC_TIE_GENERATION, IMPORT_CHANGE_SUMMARY_ASSIGNED_LOGIC, REMAINING_DURATION_DISCREPANCY, PROGRESS_OUT_OF_SEQUENCE, ACTIVITIES_RIDING_DATADATE, ACTIVITIES_SITTING_DATADATE, ONE_DAY_ACTIVITIES, BACKDATED_ACTIVITIES, ACTIVITIES_LATER_THAN_TRACKED_TO, LOE_ACTIVITIES, IMPORT_CHANGE_INCREASED_REMAINING_DURATION, NEGATIVE_NATIVE_FLOAT, CONVERGENCE_BOTTLENECKS, DIVERGENCE_BOTTLENECKS, FINISH_TO_START_RELATIONSHIP_WITH_LAG, BASELINE_EXECUTION_INDEX, MISSED_TASKS, CRITICAL_PATH_LENGTH_INDEX, or CRITICAL_PATH_TEST.

      • message string
      • value integer(int64)
      • divisor integer(int64)
      • normalizedValue number(double)
      • impact number(double)
      • indicator string

        Values are GOOD, FINE, or BAD.

    • previousScheduleCompressionIndex object
      Hide previousScheduleCompressionIndex attributes Show previousScheduleCompressionIndex attributes object
      • name string

        Values are ACTIVITIES_TOTAL, ACTIVITIES_MILESTONES, ACTIVITIES_ACTIVITIES, ACTIVITY_NAME_CHANGES, RELATIONSHIPS_TOTAL, RELATIONSHIPS_START_TO_FINISH, RELATIONSHIPS_START_TO_START, RELATIONSHIPS_FINISH_TO_START, RELATIONSHIPS_FINISH_TO_FINISH, MISSING_LOGIC, LAG_NEGATIVE, LAG_POSITIVE, CONSTRAINTS_TOTAL, CONSTRAINTS_HARD, CONSTRAINTS_SOFT, CONSTRAINT_BREAKING_LOGIC, LOW_FLOAT_ACTIVITIES, HIGH_FLOAT_ACTIVITIES, HIGH_DURATION_ACTIVITIES, RESOURCE_LOADED_ACTIVITIES, CRITICAL_PATH_PERCENT, AVG_ACTIVITY_TOTAL_FLOAT, SCHEDULE_COMPRESSION_INDEX, IMPORT_CHANGE_STARTED_NO_PROGRESS, IMPORT_CHANGE_FUTURE_ACTUAL_DATES, IMPORT_CHANGE_COMPLETE_BUT_NO_ACTUAL_FINISH_DATE, IMPORT_CHANGE_CHANGED_ACTUAL_DATES, IMPORT_CHANGE_DECREASED_PERCENT_COMPLETE, INVALID_FORECAST_DATE, MANUALLY_SCHEDULED_ACTIVITIES, DANGLING_ACTIVITIES, MANUALLY_SCHEDULED_SUMMARIES, DUPLICATE_RELATIONSHIPS, DUPLICATE_ACTIVITY_NAMES, IMPORT_CHANGE_LOGIC_TIE_GENERATION, IMPORT_CHANGE_SUMMARY_ASSIGNED_LOGIC, REMAINING_DURATION_DISCREPANCY, PROGRESS_OUT_OF_SEQUENCE, ACTIVITIES_RIDING_DATADATE, ACTIVITIES_SITTING_DATADATE, ONE_DAY_ACTIVITIES, BACKDATED_ACTIVITIES, ACTIVITIES_LATER_THAN_TRACKED_TO, LOE_ACTIVITIES, IMPORT_CHANGE_INCREASED_REMAINING_DURATION, NEGATIVE_NATIVE_FLOAT, CONVERGENCE_BOTTLENECKS, DIVERGENCE_BOTTLENECKS, FINISH_TO_START_RELATIONSHIP_WITH_LAG, BASELINE_EXECUTION_INDEX, MISSED_TASKS, CRITICAL_PATH_LENGTH_INDEX, or CRITICAL_PATH_TEST.

      • message string
      • value integer(int64)
      • divisor integer(int64)
      • normalizedValue number(double)
      • impact number(double)
      • indicator string

        Values are GOOD, FINE, or BAD.

    • forecastedScheduleCompletion string(date-time)
    • previousForecastedCompletion string(date-time)
    • health integer(int32)
    • currentStartDate string(date-time)
    • varianceStart integer(int64)
    • varianceEnd integer(int64)
    • baselineDuration integer(int64)
    • currentDuration integer(int64)
    • varianceDuration integer(int64)
    • contractualFloat integer(int64)
    • contractualEndDate string(date-time)
    • baselineContractualEndDate string(date-time)
    • varianceContractualEndDate integer(int64)
    • earnedSchedule integer(int64)
    • activitiesLaterThanTrackedTo integer(int64)
    • endDateMatch boolean
    • canImportSchedules boolean
    • totalOnTimeHitRate number(double)
GET /project/{projectId}/metrics
curl \
 --request GET 'https://live.smartpmtech.com/project/{projectId}/metrics' \
 --header "X-API-KEY: $API_KEY" \
 --header "X-COMPANY-ID: string"
Response examples (200)
{
  "projectId": 42,
  "modelId": 42,
  "name": "string",
  "id": 42,
  "source": "SmartPM",
  "scenarioType": "COMPLETE",
  "delayAnalysisPerformed": "No",
  "dataDate": "2026-05-04T09:42:00Z",
  "qualityIndex": {
    "mark": "string",
    "indicator": "GOOD",
    "score": 42.0
  },
  "baselineStartDate": "2026-05-04T09:42:00Z",
  "plannedRecovery": 42,
  "daysOfDelays": 42,
  "endDateVariance": 42,
  "underConstruction": true,
  "baselineEndDate": "2026-05-04T09:42:00Z",
  "currentScheduledCompletion": "2026-05-04T09:42:00Z",
  "previousScheduledCompletion": "2026-05-04T09:42:00Z",
  "sourceEndDate": "2026-05-04T09:42:00Z",
  "upgradePlans": [
    "string"
  ],
  "percentCompleteType": "string",
  "qualityProfileId": 42,
  "unreadNotes": 42,
  "plannedManpower": 42.0,
  "earnedManpower": 42.0,
  "remainingManpower": 42.0,
  "actualManpower": 42.0,
  "currentEstimatedManpower": 42.0,
  "plannedBudget": 42.0,
  "remainingBudget": 42.0,
  "earnedCost": 42.0,
  "manpowerPlannedPercentComplete": 42.0,
  "manpowerActualPercentComplete": 42.0,
  "manpowerPerformanceIndex": 42.0,
  "costPlannedPercentComplete": 42.0,
  "costActualPercentComplete": 42.0,
  "costPerformanceIndex": 42.0,
  "schedulePerformanceIndex": 42.0,
  "resourceCount": 42.0,
  "averageDurationVariance": 42,
  "baselineCompletionPlanned": 42.0,
  "baselineCompletionActual": 42.0,
  "completionPlanned": 42.0,
  "completionActual": 42.0,
  "performanceTrack": true,
  "costTrack": true,
  "scheduleCompressionIndex": {
    "name": "ACTIVITIES_TOTAL",
    "message": "string",
    "value": 42,
    "divisor": 42,
    "normalizedValue": 42.0,
    "impact": 42.0,
    "indicator": "GOOD"
  },
  "previousScheduleCompressionIndex": {
    "name": "ACTIVITIES_TOTAL",
    "message": "string",
    "value": 42,
    "divisor": 42,
    "normalizedValue": 42.0,
    "impact": 42.0,
    "indicator": "GOOD"
  },
  "forecastedScheduleCompletion": "2026-05-04T09:42:00Z",
  "previousForecastedCompletion": "2026-05-04T09:42:00Z",
  "health": 42,
  "currentStartDate": "2026-05-04T09:42:00Z",
  "varianceStart": 42,
  "varianceEnd": 42,
  "baselineDuration": 42,
  "currentDuration": 42,
  "varianceDuration": 42,
  "contractualFloat": 42,
  "contractualEndDate": "2026-05-04T09:42:00Z",
  "baselineContractualEndDate": "2026-05-04T09:42:00Z",
  "varianceContractualEndDate": 42,
  "earnedSchedule": 42,
  "activitiesLaterThanTrackedTo": 42,
  "endDateMatch": true,
  "canImportSchedules": true,
  "totalOnTimeHitRate": 42.0
}